Sutton Benger High Street Resurfacing update

The resurfacing work on the High Street, Sutton Benger will start on 19th June 2017 and last for three weeks. The work will be take place between 9:30am and 3:30pm, Monday to Friday.

Due to the nature of the required works and the local environment, the works are to be carried out within a temporary road closure, to ensure that adequate health and safety is maintained for local residents and the Contractor.

During the works period, access to enable residents and businesses to enter and egress from their properties will be maintained, however this could be temporarily restricted due to site operations.

The Contractor will endeavour to minimise the delay; although due to the nature of the works minor disruption is inevitable. It is essential that the road remains un-trafficked until the new material has set, as early trafficking could lead to premature failure. Dedicated Traffic Management operatives at the extent of the works will monitor access and give motorists assistance.

Access the documents:

PDF icon Extent of works

 

PDF iconDiversion details

 

PDF iconLocation details